Dayton International Airport PFC Quarterly Status Report

Revenue and Expenditures for the quarter October 1, 2025 through December 31, 2025.

Summary

Total Collection Authority: $138,930,431.00

Approved Applications
Application Impose Use Total
Application 1 (withdrawn)
Application 2
Application 3 $0.00 $28,098,728.00 $28,098,728.00
Application 4 $0.00 $45,972,854.00 $45,972,854.00
Application 5 $0.00 $27,879,176.00 $27,879,176.00
Application 6 $0.00 $2,616,158.00 $2,616,158.00
Application 7 $0.00 $7,311,845.00 $7,311,845.00
Application 8 $0.00 $27,051,670.00 $27,051,670.00
Application 9 $0.00 $0.00 $0.00
Total $0.00 $138,930,431.00 $138,930,431.00
PFC Revenue and Expenditures
Item Current Quarter Cumulative Inception to Date
PFC Revenue Collected $668,201.26 $123,930,122.97
Interest Earned (Treasury Investments) $136,770.11 $4,854,496.19
Interest from Refinancing Notes thru 9-30-07 $1,686,927.84
Total PFC Revenue Received $804,971.37 $130,471,547.00
Expenditures on Approved Projects $122,427,787.83

2025 Monthly Interest and PFC Pay-ins

2025 Monthly Interest and PFC Pay-ins
Month PFC Interest Fund (51508) PFC Master Designated Fund COD (51009)
January $2,216.40
February $171,427.19
March $145,274.11 $240,782.34
Total 1st Quarter $145,274.11 $414,425.93
April $211,635.61
May $237,293.87
June $240,481.53
Total 2nd Quarter $0.00 $689,411.01
July $153,411.96 $226,010.14
August $205,790.82
September $184,283.43 $225,520.66
Total 3rd Quarter $337,695.39 $657,321.62
Oct $216,605.50
Nov $238,836.16
Dec $136,770.11 $212,759.60
Total 4th Quarter $136,770.11 $668,201.26
2025 Total $619,739.61 $2,429,359.82

Total revenue (2025): $3,049,099.43

Project Activity: Application 4 (01-04-C-03-DAY)

Application 4 (01-04-C-03-DAY) Project Activity
Project Number Project Charge Effective Date Approval of Use Date Project Start Project Stop Current Project Expenditures Cumulative Expenditures Amount of Use Approval Current Estimated Cost
1 Runway Pavement Rehabilitation (AV0013) 7/1/2003 8/1/2002 11/00 6/05 $0.00 $989,868.00 $989,868.00 $989,868.00
2 Environmental Impact Study
(51027. 51302, 51902-AV0012, 51607)
7/3/2003 8/1/2002 1/01 12/08 $0.00 $378,965.00 $378,965.00 $378,965.00
3 Deicing System Improvements (AV0202)
51216 PBS&J WA43-08
7/5/2003 8/1/2002 7/99 6/10 $0.00 $915,824.05 $911,850.00 $911,850.00
4 Backup Generator – Airfield
51902-AV9915, 51402
7/5/2003 8/1/2002 4/01 12/06 $0.00 $1,202,813.41 $1,202,814.00 $1,202,814.00
5 ARFF Station Renovation & Expansion (51504) 7/5/2003 8/1/2002 4/00 12/02 $0.00 $1,619,191.53 $1,619,192.00 $1,619,192.00
6 Taxiway A and Z Rehabilitation
See Grants 5606 ,5706, 6107
7/5/2003 8/1/2002 4/05 12/09 $0.00 $44,240.86 $49,351.00 $49,351.00
7 Twy. H, K, E, C, L, & V (AV0013,51607,51363)
See Grants 3901, 4001, 5606 ,5706, 6107
7/5/2003 8/1/2002 11/01 12/08 $0.00 $351,718.66 $311,968.00 $311,968.00
8 Cargo & Terminal Aircraft Apron Rehabilitation
See 51302 Pvmt. Mgmt. grant 4603,
Grants 5606 , 5706, 6107 &51328
7/5/2003 8/1/2002 4/05 12/09 $0.00 $295,395.41 $300,217.00 $300,217.00
10 Land Acq.-Approach Protection – 20 – DWBA 7/5/2003 8/1/2002 4/05 10/07 $0.00 $0.00 $0.00 $0.00
11 Runway 2/20 & Other Pavement Rehab-DWBA
See 51016, 51902-AV9901
7/5/2003 8/1/2002 1/00 12/02 $0.00 $144,449.00 $144,449.00 $144,449.00
12 Land Acq.-Approach & Runway Protection
See 51222, 51902-AV9904
7/5/2003 8/1/2002 10/02 12/05 $0.00 $408,348.47 $408,394.00 $408,394.00
13 Airfield Snow Removal Equipment (6 pieces)
See fund 51230
7/1/2003 8/1/2002 10/02 12/04 $0.00 $2,278,789.00 $2,017,065.00 $2,017,065.00
14 ARFF Vehicle Replacement ( 51230) 7/1/2003 8/1/2002 10/02 12/04 $0.00 $783,334.00 $807,614.00 $807,614.00
16 Backup Generator – Terminal
51902-AV9915, 51402
7/1/2003 8/1/2002 1/03 12/06 $0.00 $1,202,813.40 $1,202,814.00 $1,202,814.00
17 Terminal Gate Expansion
See 51902-AV0004, 51301, 51525
7/1/2003 8/1/2002 10/00 12/08 $0.00 $19,160,479.02 $19,191,396.00 $19,191,396.00
18 Terminal Drive & Related Roads Rehab.51506,
51306, 51457, 51524, 51511, 51902-AV9906,
51663 & 51620.
7/1/2003 8/1/2002 1/03 12/09 $0.00 $4,754,228.38 $3,725,623.00 $3,725,623.00
19a SW Term Apron/NE Deice/Perimeter Rd.
(51902-AV0001, AV0005, 51015)
7/1/2003 8/1/2002 4/00 6/03 $0.00 $1,723,528.00 $1,723,528.00 $1,723,528.00
19b CALCS (51015) 7/1/2003 8/1/2002 4/00 6/03 $0.00 $44,480.00 $44,480.00 $44,480.00
20 Pt. 150 Noise Studies (51902-AV9902, 51316) 7/1/2003 8/1/2002 1/99 12/07 $0.00 $624,890.26 $570,685.00 $570,685.00
22 Airport Police Office Renovation (1) – fund 51601 7/1/2003 8/1/2002 6/97 7/99 $0.00 $265,894.00 $265,894.00 $265,894.00
Subtotal $0.00 $37,189,250.45 $35,866,167.00 $35,866,167.00
Debt Interest Paid $51,896.65 $10,795,007.90 $10,106,687.00 $10,106,687.00
Total $51,896.65 $47,984,258.35 $45,972,854.00 $45,972,854.00

Project Activity: Application 5 (05-05-C-01-DAY)

Application 5 (05-05-C-01-DAY) Project Activity
Project Number Project Charge Effective Date Approval of Use Date Project Start Project Stop Current Project Expenditures Cumulative Expenditures Amount of Use Approval Current Estimated Cost
1 Terminal Environment Restoration 12/1/2013 8/19/2005 7/98 5/02 $0.00 $8,797,981.00 $8,797,981.00 $8,797,981.00
2 In-Line Baggage Make-up Facility 12/1/2013 8/19/2005 10/07 2/11 $0.00 $11,787,497.45 $11,325,432.00 $11,325,432.00
Subtotal $0.00 $20,585,478.45 $20,123,413.00 $20,123,413.00
Debt Interest Paid $59,616.64 $6,419,835.75 $7,755,763.00 $7,755,763.00
Total $59,616.64 $27,005,314.20 $27,879,176.00 $27,879,176.00

Project Activity: Application 8 (15-08-C-00-DAY)

Application 8 (15-08-C-00-DAY) Project Activity
Project Number Project Charge Effective Date Approval of Use Date Project Start Date Project Stop Date Current Quarter Pay-as-Go Current Quarter Debt Principal Payment Current Quarter Debt Interest Payment Current Quarter Combined Expenditures Cumulative Pay-as-Go Cumulative Debt Principal Payment Cumulative Debt Interest Payment Cumulative Combined Project Expenditures Amount of Use Approval Remaining Authority
1 Airport Terminal Renovations-Phase II 4/1/19 1/14/16 5/1/13 1/1/27 $276,822.88 $300,172.43 $576,995.31 $4,224,887.71 $6,334,343.92 $10,559,231.63 $26,951,670.00 $16,392,438.37
2 PFC Administration Costs 4/1/19 1/14/16 3/1/14 12/1/35 $0.00 $0.00 $48,404.00 $48,404.00 $100,000.00 $51,596.00
Totals $576,995.31 $10,607,635.63 $27,051,670.00

Project Activity: Application 9 (25-09-C-00-DAY)

Application 9 (25-09-C-00-DAY) Project Activity
Project Number Project Charge Effective Date Approval of Use Date Project Start Project Stop Current Project Expenditures Cumulative Expenditures Amount of Use Approval Current Estimated Cost
009-001 Runway 6L/24R Rehabilitation, Phase 2 2/1/2029 10/14/25 6/1/15 11/1/15 $0.00 $0.00 $1,061,583.00 $1,061,583.00
009-002 Environmental Mitigation – West Perimeter Road Stream 2/1/2029 10/14/25 6/1/15 11/1/15 $0.00 $0.00 $21,323.00 $21,323.00
009-003 Runway 18/36 Rehabilitation 2/1/2029 10/14/25 4/1/18 2/1/20 $0.00 $0.00 $820,309.00 $820,309.00
009-004 Rehabilitate Runway 18/36 Distance Remaining Signs 2/1/2029 10/14/25 4/1/18 2/1/20 $0.00 $0.00 $3,200.00 $3,200.00
009-005 Rehabilitate Terminal Apron Phases 1a and 1b (FAA Phases 1 and 2 of 9) 2/1/2029 10/14/25 3/1/16 12/1/16 $0.00 $0.00 $411,464.00 $411,464.00
009-006 Rehabilitate Terminal Apron Phases 2a, 2b and 2c (FAA Phases 3, 4 and 5 of 9) 2/1/2029 10/14/25 7/1/18 10/1/20 $0.00 $0.00 $1,047,784.00 $1,047,784.00
009-007 Rehabilitate Terminal Apron Phase 3 (FAA Phase 6 of 9) 2/1/2029 10/14/25 3/1/20 2/1/21 $0.00 $0.00 $368,302.00 $368,302.00
009-008 Rehabilitate Terminal Apron Phase 4 (FAA Phase 7 of 9) 2/1/2029 10/14/25 8/1/22 11/1/24 $0.00 $0.00 $1,352,298.00 $1,352,298.00
009-009 Acquire Aircraft Rescue and Fire Fighting Equipment 2/1/2029 10/14/25 11/1/19 11/1/24 $0.00 $0.00 $75,487.00 $75,487.00
009-010 Airport Master Plan Update 2/1/2029 10/14/25 10/1/19 4/1/24 $0.00 $0.00 $143,938.00 $143,938.00
009-011 Improve Terminal Building (Public Circulation Enhancement) 2/1/2029 10/14/25 2/1/22 11/1/23 $0.00 $0.00 $476,072.00 $476,072.00
009-012 Rehabilitate Airfield Electrical Vault and Emergency Generator 2/1/2029 10/14/25 7/1/24 6/1/25 $0.00 $0.00 $99,470.00 $99,470.00
009-013 Concourses A & B Escalator Rehabilitation 2/1/2029 10/14/25 10/1/23 5/1/25 $0.00 $0.00 $162,570.00 $162,570.00
009-014 Replace Passenger Loading Bridges, Phases 1 and 2 (2024) 2/1/2029 10/14/25 5/1/25 5/1/26 $0.00 $0.00 $847,143.00 $847,143.00
009-015 Replace Passenger Loading Bridges, Phase 3 (2025) 2/1/2029 10/14/25 9/1/25 12/1/26 $0.00 $0.00 $344,111.00 $344,111.00
009-016 Replace Passenger Loading Bridges, Phase 4 (2026) 2/1/2029 10/14/25 9/1/26 12/1/27 $0.00 $0.00 $262,500.00 $262,500.00
009-017 Replace Inbound Baggage Carousels 2/1/2029 10/14/25 9/1/25 9/1/26 $0.00 $0.00 $3,200,000.00 $3,200,000.00
009-018 Acquire Snow Removal Equipment 2/1/2029 10/14/25 9/1/25 12/1/26 $0.00 $0.00 $3,000,000.00 $3,000,000.00
009-019 Install Airfield Guidance Signs 2/1/2029 10/14/25 8/1/25 8/1/26 $0.00 $0.00 $132,800.00 $132,800.00
009-020 Rehabilitate Taxiway “W” Phase 1 of 3 2/1/2029 10/14/25 9/1/25 12/1/26 $0.00 $0.00 $130,502.00 $130,502.00
009-021 Rehabilitate Taxiway “W” Lighting, Phase 1 of 3 2/1/2029 10/14/25 9/1/25 12/1/26 $0.00 $0.00 $67,498.00 $67,498.00
009-022 PFC Administration Costs 2/1/2029 10/14/25 10/1/24 5/1/37 $0.00 $0.00 $100,000.00 $100,000.00
Total $0.00 $0.00 $14,128,354.00 $14,128,354.00